Wressle Project Update
October 18, 2023
Workover operations on the Wressle-1 well to install a downhole jet pump and recomplete the well have been successfully concluded. The workover rig has been demobilised from the Wressle site.
A new surface Triplex pump has been purchased and has been installed and connected. The final stages of the surface facilities upgrades are nearing completion. The re-instatement of production operations at Wressle-1 well is currently expected during the week commencing 23 October 2023.
Egdon hold a 30% economic interest in PEDL180/182.